This project consisted of approximately 29,000 LF of a new 24-inch water main and the upgrade of an existing water booster station to a firm capacity of 6.5 MGD. CJS provided design, survey, easement mapping, permitting, and bid phase assistance for the project. The new booster pump station site consists of a prefabricated duplex packaged […]

Projects

Each year, the Town of Cary identifies locations throughout the well-established areas of  town where water mains have exceeded their useful life and need to be replaced.. CJS has served as the Town’s on-call consultant for these replacements since 2020, having been selected/renewed for five separate contracts. The project areas are located in various neighborhood […]

Projects

A large diameter sewer project including preliminary engineering evaluations, environmental investigations, easement survey and mapping, design, bidding, and construction phase services for the construction of approximately 26,000 LF of 84-inch and 96-inch sewer interceptor along the east side of the Neuse River. The project included design of the City’s largest single gravity sewer, abandonment of […]

Projects

After completing a study and preliminary engineering report, CJS recommended constructing approximately 8,200 feet of 16-inch gravity sewer to abandon the Duchess Downs WWPS and redirect its flows to the Adam Pointe WWPS. CJS is now providing design, permitting, easement surveying and mapping, environmental investigations, bid and construction phase assistance, and record drawings for the […]

Projects

CJS assisted OWASA with a multi-year water main replacement program across 10 high-profile project areas in Chapel Hill, NC, providing planning through construction services for 30,000 LF of 6-inch, 8-inch, and 12-inch asbestos cement water main replacements. Settings included residential neighborhoods, busy UNC campus thoroughfares, and major NCDOT roadways. One critical segment ran through active […]

Projects

NC State Parks was recently approved for approximately $40 million in American Rescue Plan Act (ARPA) funding to support infrastructure upgrades across the park system. In partnership with Finch & Associates, CJS is delivering water and sewer improvements at seven parks across the state: Hammocks Beach State Park, Jordan Lake State Recreation Area, Falls Lake […]

Projects

CJS supported Raleigh Water on an on-call effort to replace and rehabilitate aging infrastructure in the Buck Jones Road area of southwest Raleigh. In anticipation of future development, the project improved system integrity and reliability through the CCTV inspection of 9,310 LF of vitrified clay sewer mains, the design and replacement of 3,955 LF of […]

Projects

Raleigh Water identified low-pressure issues within the Town of Zebulon linked to undersized and tuberculated lines. Based on system evaluations, a mix of rehabilitation and replacement was recommended. CJS was engaged via our on-call contract with the City to provide design, permitting, right-of-entry mapping, bidding, and record drawings for the replacements project, as well as […]

Projects

This project consisted of a 3,100 LF of new 24-inch ductile iron reinforcing water main within the road pavement of NW Maynard Road, with connections at High House Road and Old Apex Road, and three bore and jack installations. Additionally, the project included the construction of approximately 1,800 feet of new sidewalk and handicap ramps. […]

Projects

This project involves the design of a new 1 MGD prefabricated potable water booster station and upgrades to existing piping and valves at the Brynn Marr Elevated Water Storage Tank. The project began with an evaluation phase that included field data collection, hydraulic modeling, and analysis of hydraulic performance, operational benefits, construction constraints, and costs. […]